EMC Isilon Solutions and Design Specialist Exam for Technology Architects E20-555 Question # 65 Topic 7 Discussion

EMC Isilon Solutions and Design Specialist Exam for Technology Architects E20-555 Question # 65 Topic 7 Discussion

E20-555 Exam Topic 7 Question 65 Discussion:
Question #: 65
Topic #: 7

A customer has two data centers (Site A and Site B).There is an Isilon cluster in each data center and they use SyncIQ to replicate data between the two data centers.

You have reviewed their disaster recovery plan and found the following:

    The policies specify that SyncIQ runs a replication job every 3 hours and that the job finishes within 1 hour.

    Three additional hours will be needed to get servers and the network redirected to work from Site B.

What is the Recovery Point Objective in this plan?


A.

2 Hours


B.

3 Hours


C.

4 Hours


D.

5 Hours