A VxRail Test Plan has been completed What is the protocol for recording the results'?
With the implementation team, complete and document each test, test date, and a screenshot of results
In front of a customer, complete each test and document the test date
With the implementation team, complete each test and document the test date
In front of a customer, complete and document each test, test date, and a screenshot of results