EMC Dell RecoverPoint Operate Achievement D-RP-OE-A-24 Question # 9 Topic 1 Discussion

EMC Dell RecoverPoint Operate Achievement D-RP-OE-A-24 Question # 9 Topic 1 Discussion

D-RP-OE-A-24 Exam Topic 1 Question 9 Discussion:
Question #: 9
Topic #: 1

A database team is performing tests against a PIT copy of data. Their write activity is going to exceed the currently allocated amount of space dedicated to Image Access mode.

What should be done to allow testing to continue without disruption to their testing?


A.

Navigate to Protection > Manage Protection > Select the CG from the list and select the copy.

Click Edit Journal, and add one or more additional Journal volumes.


B.

Use the config_copy_group= copy= policy image_access_log_size= CLI command


C.

Expand the Journal volume using native array tools.

Navigate to Protection > Manage Protection > Select the CG from the list and select the copy.

Click Edit Journal, and then select "Expand Journal".


D.

Navigate to Protection > Manage Protection > Select the CG from the list and select the copy.

Click Edit, and then increase the reserved image access percentage from 20%