D-PVM-OE-01 Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

An SRDF/Metro pair was created with vWitness After a network outage, the administrator discovers that the SRDF pair is in an ActiveBias state What is the correct sequence of events to bring the SRDF pair into an ActiveActive state?

D-PVM-OE-01 Question 21