Scope creep refers to the uncontrolled expansion of a project’s objectives, deliverables, or requirements beyond the original scope as defined in the project plan, without corresponding increases in resources or timelines.
Key Characteristics:
Often results from lack of proper change management.
Can cause budget overruns, missed deadlines, and resource strain.
Why Not Other Options:
Deadline extension (B): Refers to extending the project timeline, not scope changes.
Scope modification (C): Implies controlled and approved changes to the scope.
Deliverable expansion (D): Does not specifically address the lack of control involved in scope creep.
EC-Council CISO Guidance:
Effective project management requires robust change management processes to prevent scope creep while ensuring stakeholder alignment.