Which of the following activities must be completed BEFORE you can calculate risk?


A.

Determining the likelihood that vulnerable systems will be attacked by specific threats


B.

Calculating the risks to which assets are exposed in their current setting


C.

Assigning a value to each information asset


D.

Assessing the relative risk facing the organization’s information assets