Jake was preparing a particular plan for his organization in which all personnel accountable for research, development, and implementation of the disaster recovery plan were being identified. Which plan was Jake preparing for his organization?
A Disaster Management Plan identifies personnel for research, development, and implementation of disaster-related strategies, broader than just DR, as Jake did.
Option A (BCP):Focuses on continuity, not personnel identification alone.
Option C (IT Recovery):IT-specific, narrower scope.
Option D (DRP):Recovery-focused, not as broad as management.
“The Disaster Management Plan assigns personnel for research, development, and implementation, encompassing all disaster response aspects” (Module: Disaster Recovery Planning, Section: Management Plans).