Dassault Systemes V6 ENOVIA V6 Program Central (V6R2012) ENOV612-PRG Question # 40 Topic 5 Discussion

Dassault Systemes V6 ENOVIA V6 Program Central (V6R2012) ENOV612-PRG Question # 40 Topic 5 Discussion

ENOV612-PRG Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

A resource loading report is used to display the hours for:


A.

all the users for a set period


B.

a person for a specific task


C.

a set of users for a given period


D.

all the users for a given project


Get Premium ENOV612-PRG Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.