Dassault Systemes V6 ENOVIA V6 Program Central (V6R2012) ENOV612-PRG Question # 23 Topic 3 Discussion
ENOV612-PRG Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3
You have a 2 day fixed task with these dates: Start: Thur Jul 24, 2003 End: Fri Jul 25, 2003, you have a 2 day dependent fixed task that is set for FF+1.0 d then the dependent task will have this:
A.
Estimated Start Date Fri Jul 25, 2003 And this Estimated Finish Date Mon Jul 28, 2003
B.
Estimated Start Date Wed Jul 23, 2003 And this Estimated Finish Date Thur Jul 24, 2003
C.
Estimated Start Date Thur Jul 24, 2003 And this Estimated Finish Date Fri Jul 25, 2003
D.
Estimated Start Date Tues Jul 29, 2003And this Estimated Finish Date Wed Jul 30, 2003
Chosen Answer: