Dassault Systemes V6 ENOVIA V6 Program Central (V6R2012) ENOV612-PRG Question # 3 Topic 1 Discussion

Dassault Systemes V6 ENOVIA V6 Program Central (V6R2012) ENOV612-PRG Question # 3 Topic 1 Discussion

ENOV612-PRG Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

When you copy a WBS from another project, the task Estimated Start and End dates:

ENOV612-PRG Question 3


A.

are cleared


B.

have the original dates


C.

are cleared and then recomputed based on the start date of the project and on the task dependencies


D.

will have the new project created date


Get Premium ENOV612-PRG Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.