PerDFARS 252.204-7021, contractors must achieve the requiredCMMC certification levelbefore contract awardif the solicitation specifies it.
Key Requirements:✔Contractorsmust be certified at the required CMMC levelprior to contract award.
✔Thecertification must be conducted by a C3PAO(for Level 2) orthrough self-assessment(for Level 1).
✔The certification must bevalid and registered in the Supplier Performance Risk System (SPRS)before award.
A. At the time of award → Correct
DFARS 252.204-7021requires CMMC certification before a contract can be awardedif the solicitation includes CMMC requirements.
B. Upon solicitation submission → Incorrect
Contractorsdo notneed to be CMMC-certified at thetime of bid submission, only by the time of award.
C. Thirty days from the award date → Incorrect
Contractorsmust already be certified before the award is granted. There isno grace period.
D. Before the due date of submission → Incorrect
While compliance planning is important,CMMC certification is only required before contract award, not before bid submission.
Why is the Correct Answer "At the Time of Award" (A)?
DFARS 252.204-7021 (CMMC Requirement Clause)
CMMC certification is required prior to contract awardif specified in the solicitation.
CMMC 2.0 Program Overview
States that certificationis not needed at bid submission but is required before award.
DoD Interim Rule & SPRS Guidance
Contractors must havea valid CMMC certification recorded in SPRSbefore award.
CMMC 2.0 References Supporting This Answer:
Submit