The Lead Assessor concludes that the OSC is not ready for the assessment. After the Readiness Assessment Review, the OSC and the Lead Assessor could choose to:
The CMMC Assessment Process (CAP) provides explicit guidance for readiness reviews. If the Lead Assessor determines that the OSC is not prepared, the available options are:
Replan the assessment (adjust scope, timeline, or requirements), or
Reschedule the assessment (move the engagement to a later date).
Extract:
“Following the readiness review, if the OSC is determined not to be ready, the Lead Assessor may recommend that the assessment be replanned or rescheduled.”
Thus, the correct answer is B.
[Reference: CMMC Assessment Process (CAP), Readiness Review section., ]