Question #: 15
Topic #: 2

What is the correct sequence of steps involved in scheduling a threat intelligence program?

1. Review the project charter

2. Identify all deliverables

3. Identify the sequence of activities

4. Identify task dependencies

5. Develop the final schedule

6. Estimate duration of each activity

7. Identify and estimate resources for all activities

8. Define all activities

9. Build a work breakdown structure (WBS)


A.

1-->9-->2-->8-->3-->7-->4-->6-->5


B.

3-->4-->5-->2-->1-->9-->8-->7-->6


C.

1-->2-->3-->4-->5-->6-->9-->8-->7


D.

1-->2-->3-->4-->5-->6-->7-->8-->9