During the construction documents phase, CSI’s guidance emphasizes that coordination between the architect/engineer (A/E) and the various consulting disciplines (structural, mechanical, electrical, etc.) is essential to produce consistent, coordinated, and complete contract documents (drawings, specifications, and project manual). Part of that coordination is a shared quality assurance (QA) effort among the design team members.
In CSI’s practice guides and CDT body of knowledge, the following principles are stressed (paraphrased to respect copyright):
The prime design professional is responsible for overall coordination of the construction documents, but each consultant is responsible for the technical accuracy and coordination of their own portions.
Coordination includes review of cross-references, matching terminology, alignment of requirements between drawings and specifications, and resolving conflicts before bid/issue.
Quality assurance during this phase is not done in isolation; it is a team activity. Consultants and the lead design firm review each other’s work where it interfaces (e.g., architectural and mechanical coordination of ceilings and diffusers; structural and architectural coordination of openings, etc.).
Therefore, “Quality assurance tasks shared between design and consulting teams” (Option D) correctly describes a standard component of project design team coordination during the construction documents phase.
Why the other options are incorrect:
A. Duplication of important information by each disciplineCSI stresses “say it once, in the right place” as a fundamental principle. Information should not be unnecessarily duplicated because duplication increases the risk of conflict and inconsistency (for example, a requirement shown in both drawings and multiple spec sections but updated in only one location). Coordination aims to avoid duplication, not to promote it.
B. Ensuring drawing note terminology is differentiated from specification terminologyCSI emphasizes consistent terminology across drawings, specifications, and other documents. The same items (e.g., “gypsum board,” “reinforcing steel,” “membrane roofing”) should be described using the same terms in both drawings and specifications to reduce ambiguity. Coordination meetings often include checking that terminology is aligned, not intentionally differentiated.
C. Requiring the owner to hire a third-party to write the Division 01 specifications independentlyDivision 01 – General Requirements – is typically prepared or controlled by the lead design professional or specifier, in coordination with the owner. CSI materials do not identify it as a standard or required coordination practice for the owner to hire an independent third party to write Division 01 separately from the design team. That may occur on some projects, but it is not a defined component of team coordination in CSI’s CDT framework.
In summary, CSI-based construction documentation practice defines coordination during the construction documents phase as a shared responsibility among the architect/engineer and all consultants, including joint quality assurance reviews, consistency checks, and cross-discipline coordination. This aligns directly with Option D.
Key CSI References (no links):
CSI Project Delivery Practice Guide – chapters on Design Phase and Construction Documents coordination.
CSI Construction Specifications Practice Guide – sections on coordination between drawings and specifications and the role of Division 01.
CSI CDT Body of Knowledge – topics on roles and responsibilities of the design team and coordination of construction documents.