CSI and standard General Conditions define the architect/engineer’s submittal review purpose as confirming that submittals conform to the design intent shown and specified in the contract documents — not to approve means, methods, or to revise design.
The A/E’s review checks:
General compliance of the submittal with design intent.
Coordination among trades.
Any deviations that require clarification or change approval.
It is not for:
Designing or redesigning (Option A),
Supervising construction procedures (Option C), or
Evaluating formal substitution requests (Option D) — substitutions are separately submitted for approval under Division 01 procedures.
Therefore, the A/E reviews submittals to monitor design conformance, making Option B correct.
CSI Reference:
CSI Construction Specifications Practice Guide, “Submittal Procedures and Responsibilities”; Project Delivery Practice Guide, “Construction Phase — Submittal Review.”