CDT Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

The architect/engineer reviews submittals for which of the following reasons?


A.

To correct or change the design


B.

To monitor design conformance


C.

To review installation procedures


D.

To review substitution requests