Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

CompTIA Project+ Certification (2026) PK0-005 Question # 133 Topic 14 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 133 Topic 14 Discussion

PK0-005 Exam Topic 14 Question 133 Discussion:
Question #: 133
Topic #: 14

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?


A.

ESG


B.

PHI


C.

Pll


D.

ROI


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.