PK0-005 Exam Topic 11 Question 109 Discussion:
Question #: 109
Topic #: 11

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?


A.

Rollback plan


B.

Downtime stage


C.

Maintenance window


D.

Validation checks