CompTIA Project+ Certification (2025) PK0-005 Question # 99 Topic 10 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 99 Topic 10 Discussion

PK0-005 Exam Topic 10 Question 99 Discussion:
Question #: 99
Topic #: 10

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers

• High uncertainty about existing systems

• Risk of frequent requirement changes

• Tight deadlines

Which of the following project methodologies would be best to use in this situation?


A.

PRINCE2


B.

Scrum


C.

SAFe


D.

XP


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.