Question #: 27
Topic #: 3

Harry is negotiating a contract for a new IT system for his business. He is investing heavily in the system and wants the system to be able to provide the services he requires for the next 10 years. However he is aware that technology is changing quickly and would like to include a clause in the contract to ensure that the system he is purchasing is useable for the next 10 years. What should Harry include in the contract?


A.

limitation of liability


B.

service credits


C.

benchmarking


D.

change control