L5M3 Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

Verity Fashion is a clothing manufacturer and has an order to create 10,000 pairs of flipflops for a retailer for the summer. The order was placed over the phone in February. The order has been completed and has been boxed up ready for delivery. The retailer calls Verity Fashion in June and says that the order is no longer required. What action can Verity Fashion take?


A.

sue for damages as the flip flops have already been made and this incurred costs


B.

nothing- there is no written contract in place


C.

subcontract the manufacturing of the flipflops to a third party


D.

claim on insurance