Question #: 54
Topic #: 6

The procurement manager of a private healthcare provider is running an IT project. Who would be the stakeholders?

    General public

    Pharmaceutical suppliers

    Senior Management

    Software support developers


A.

2 and 4 only


B.

1 and 3 only


C.

1 and 2 only


D.

3 and 4 only