If tenders are received by electronic submission exclusively, the buyer can reduce the timescale. On average the time for a standard tender submission can be reduced by 5 days if bids are submitted electronically.
*Note* this is based off current PCR Regs 2015 which are being superseded in October 2024 by new legislation. We currently don't know what the new regs will say on this. If it's different, my best guess is CIPS will remove any question about it from their exam- because the study guide would be wrong and that would lead to complaints.