L4M3 Exam Topic 6 Question 55 Discussion:
Question #: 55
Topic #: 6

An organization has a normal tender process that often last 1 month from defining the needs to contract award. Manufacturing department suddenly required a new special part that they could not foresee within a month. Which of the following should be the priority actions of procurement manager in this urgent situation? Select TWO that apply:


A.

Design new specification


B.

Develop relationships with potential suppliers


C.

Review contract performance


D.

Get high-level authority approval


E.

Submit full business justification