Question #: 46
Topic #: 5

Which of the following would be suitable key performance indicators (KPIs) for supplier performance?

Ensure you have customer loyalty

Value or percentage of cost reductions obtained

Win an award in the next 12 months

Percentage of on-time in full deliveries


A.

1 and 3 only


B.

2 and 4 only


C.

1 and 4 only


D.

2 and 3 only