L4M3 Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

A manufacturing company signed a contract with a raw material supplier. The contract includes a clause on liquidated damages in case of late delivery. Purchaser was obliged to pay after 30 days from delivery. Eventually raw material was delivered 1 week later than initial plan due to supplier’s slow production process. There is no defect in the delivered batch. Which of the following can be claimed by the manufacturing company?


A.

Rights to refunds or repairs


B.

Right of set-off


C.

Right of third party


D.

Right of extending payment