Main risks involved in an under-specified requirement
• The product or service is not fit for use since it does not match the actual needs
• Higher cost due to corrections or reworks (proposal evaluations, scope or work monitoring, change in insulation materials or systems, reduced productivity, etc.).
• Higher operating cost on many fronts: process control, energy consumption, maintenance, etc.
• Other problems like corrosion under insulation, mold development, safety-related concerns, etc.
LO 3, AC 3.3