Question #: 65
Topic #: 7

A company is planning the procurement of an IT system and wants to agree a through-life contract with the supplier to ensure ongoing system support. The first step in producing that specification should be to:


A.

Build a design


B.

Prepare tendering documents


C.

Identify the IT system supplier


D.

Define the user requirements