L4M2 Exam Topic 4 Question 39 Discussion:
Question #: 39
Topic #: 4

A procurement manager decided to use a conformance specification in a request for quotation (RFQ) for the manufacturing of a specialist item designed by their company. The company does not have the capability to manufacture the item in-house, but requires the item to be made to their detailed specification. Was this the correct thing to do?


A.

Yes, as it means that the company will be able to get the most cost-effective price for the item from the chosen supplier


B.

Yes, as it means that the company will get exactly what it has specified and meets its specific requirements


C.

No, as the item will be of non-standard construction and will not be able to be used by other competitors


D.

No, as it means that the chosen supplier will not be able to use their expertise and knowledge to manufacture the item