A procurement manager is discussing with other stakeholders about the scope and the implementation of the upcoming construction project. A stakeholder argues that the construction projects are often risky as the overall scope of the work can't be accurately estimated from the beginning. Furthermore, the project spans over a long period, the costs of materials can fluctuate widely. The procurement manager suggests that the pricing structure should be able to cover the supplier's costs plus 10% markup on total costs. This arrangement is known as...?


A.

Cost-plus fixed-fee


B.

Cost-plus award fee


C.

Cost-plus incentive fee contracts


D.

Cost-plus Fixed percentage