Question #: 6
Topic #: 1

Which of the following are true about a Blue Prism Breakpoint?

(Select all items that apply)


A.

The Process can be run in Control Room and the session will stop once it reaches the stage which has been assigned a Breakpoint


B.

A Breakpoint will force the Process to terminate


C.

The Developer can run the Process in Studio and the Process will stop at the stage which has been assigned a Breakpoint.


D.

Breakpoints are ignored when a Process in run in Control Room


E.

A Breakpoint will pause a Process for a defined period of time, at the stage which has been assigned the Breakpoint Once this time has elapsed, the Process will move onto the next stage.