If a conduit run between two pull boxes has two 90-degree bends and measures 23 m (75 ft) total in length, what is the BEST way to comply with BICSI recommendations if you need to add a third 90-degree bend?
A.
Lubricate the conduit heavily and pull the cable in one continuous run
B.
Replace the entire run with larger conduit
C.
Add an appropriately placed pull box or intermediate point
D.
Use a flexible metallic conduit for the final bend
Chosen Answer: