DCDC-002 Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

What is the clearance required between AC units?


A.

Min. of 2 ft but recommended 6 ft.


B.

Min. of 4 ft but recommended 6 ft.


C.

Min. of 6 ft but recommended 8 ft.


D.

Min. of 8 ft but recommended 10 ft.