TM12 Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

You are following a risk-based testing strategy. The test execution time is very limited. Assume that all the product risk items require moreor less the same level of test effort.

TM12 Question 19

Which of the following answers describes the best execution schedule in this scenario?

Number of correct responses: 1

K33 credits


A.

1- Test the acceptance of transactions coming from the IVR channel

2- Test the correct charge of the Smart Card with the required contents

3- Test the correct pre-activation of the Smart Card

4- Test the correct activation of the Smart Card


B.

1- Test the correct pre-activation of the Smart Card

2- Test the correct charge of the Smart Card with the required contents

3- Test the correct activation of the Smart Card

4- Test the acceptance of transactions coming from the IVR channel


C.

1- Test the correct activation of the Smart Card

2- Test the correct pre-activation of the Smart Card

3- Test the correct charge of the Smart Card with the required contents

4- Test the acceptance of transactions coming from the IVR channel


D.

1- Test the correct pre-activation of the Smart Card

2- Test the correct activation of the Smart Card

3- Test the correct charge of the Smart Card with the required contents

4- Test the acceptance of transactions coming from the IVR channel