BCI Certificate of the Business Continuity Institute (CBCI) CBCI Question # 51 Topic 6 Discussion

BCI Certificate of the Business Continuity Institute (CBCI) CBCI Question # 51 Topic 6 Discussion

CBCI Exam Topic 6 Question 51 Discussion:
Question #: 51
Topic #: 6

When preparing to carry out a Business Impact Assessment (BIA), the Business Continuity professional should:


A.

Review all relevant organization documents to help assess the appropriate parameters and factors to be applied during the process


B.

Consult with personnel to determine preferred ways of working in different departments


C.

Consider the potential recovery strategies and solutions that may be implemented


D.

Ensure that the process includes an external communications procedure