CSSBB Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

A team has brainstormed a large number of possible drivers of process issues for which other data is not readily available. What tool should the team use to identify the connection between various issues to determine the key drivers?


A.

Interrelationship digraph


B.

Cause and effect diagram


C.

Correlation analysis


D.

Design of experiments