CMQ-OE Exam Topic 4 Question 32 Discussion:
Question #: 32
Topic #: 4

The manager for a quality improvement project at an organization receives the project charter during the initiation phase of a project.

‘Which of the following information should the expect to find in this document?


A.

The initial project requirements, constraints, and assumption


B.

The work breakdown description (WBS) for the project


C.

The communications plan for this project


D.

The detailed risk assessment and the corresponding contingency plans for each risk