ASQ Certified Construction Quality Manager CCQM Question # 43 Topic 5 Discussion

ASQ Certified Construction Quality Manager CCQM Question # 43 Topic 5 Discussion

CCQM Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5

Which of the following is the best benefit of aligning the project quality plan with other management plans?


A.

It integrates the quality plan into organizational objectives.


B.

It identifies any conflicts between the quality plan and financial objectives.


C.

It promotes buy-in from the project team when adopting the quality plan.


D.

It demonstrates why the quality plan should take precedence over other plans.