Question #: 42
Topic #: 5

Why is it important to have clear contract criteria during the bidding process?


A.

It allows bidders to align their bids with project requirements.


B.

It helps the project complete under budget.


C.

It decreases the time spent on bid evaluation and vendor selection.


D.

It minimizes legal disputes with bidders.