When a project faces significant scope changes, including the addition of new features halfway through, how should a Construction Quality Manager evaluate and prioritize inspections?
A.
Prioritize inspections based on the original project plan and impact on schedule.
B.
Focus inspections and testing on new project elements, instead of on established parts of the construction.
C.
Concentrate inspections primarily on areas where the most resources have been allocated.
D.
Reassess and prioritize inspections based on the new elements' criticality and their potential impact on project integrity.
When a project undergoes significant scope changes, including the addition of new features midway through construction, it is crucial to reassess and prioritize inspections to ensure structural integrity, compliance, and overall quality.
Assessing the Impact of New Elements
New project elements may introduce additional risks, require different materials, or alter the structural load distribution. Inspections should be reprioritized to focus on these new elements’ impact on the entire project.
Three-Phase Control System in Construction
The Three-Phase Control System (Preparatory, Initial, and Follow-up phases) ensures quality compliance. When scope changes occur, each phase should be revisited to account for modifications.
The preparatory phase should be updated to redefine quality expectations, the initial phase should establish specific testing protocols for new elements, and the follow-up phase should monitor adherence to revised standards.
Mitigating Risk and Ensuring Compliance
A significant scope change affects the project's safety, compliance, and quality. Prioritizing inspections based on the criticality of the new elements ensures that no structural weaknesses or compliance issues arise.
Project Integrity and Long-Term Performance
ASQ and DOE quality management principles highlight that project changes should be integrated into the existing quality management system without compromising the integrity of the overall structure.
Delayed or improperly planned inspections can lead to undetected defects, requiring costly corrections later.
Detailed JustificationThus, reassessing and reprioritizing inspections based on new elements’ criticality ensures project integrity, compliance, and overall construction quality.