What should be prioritized when developing a system to monitor time-related risks and minimize delays in a project?


A.

The system should focus on identifying and addressing early warning signs of delays.


B.

The system should prioritize rapidly executing phases of work in sequence.


C.

Effectiveness is determined by how often schedule updates are shared with stakeholders.


D.

Evaluate adherence to the project timeline and prioritize the schedule over risk.