CCQM Exam Topic 4 Question 30 Discussion:
Question #: 30
Topic #: 4

What strategy should be used to ensure that interpretations of CoQ data accurately reflect the quality costs' impact on the organization?


A.

Compare CoQ data with internal success metrics to assess impact on operational efficiency


B.

Compare all CoQ data against industry standards regardless of context to assess impact on operational efficiency


C.

Base interpretations on cost data from the most recent project


D.

Use qualitative feedback from team members as the basis for interpretation