CCQM Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

How should complaint logs be used to improve the quality management system in a construction project?


A.

Review complaint logs quarterly to avoid being overwhelmed by the volume of data.


B.

Disregard minor complaints to focus resources on repeated or severe issues.


C.

Limit the review of complaint logs until the project is complete to assess overall performance.


D.

Maintain a real-time, accessible complaint log and conduct monthly reviews to identify emerging issues.