Question #: 24
Topic #: 3

What is the primary purpose of design verification in the construction project management process?


A.

Confirm that design outputs fulfill the design inputs


B.

Check if the final construction matches the initial design ideas using visual assessments


C.

Determine the cost-effectiveness of the design outputs


D.

Evaluate the performance of the construction team