CCQM Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

Corrective strategies implemented to resolve customer complaints in a construction project should


A.

assume any decrease in complaints indicates a successful strategy


B.

evaluate the effectiveness based on the speed of complaint resolution


C.

measure customer satisfaction before and after the implementation of corrective actions


D.

rely on customer testimonials as the measure of strategy success