Question #: 13
Topic #: 2

Which of the following approaches best allows a project manager to determine key stakeholders involved in the design process for each discipline?


A.

Analyzing the project scope and identifying which disciplines have significant impacts on project outcomes


B.

Limiting stakeholder involvement to those with financial investments in the project


C.

Involving senior management from each discipline as key stakeholders


D.

Choosing stakeholders based on their availability rather than their impact on the design process