Question #: 50
Topic #: 6

A company has selected a project manager to upgrade security at its manufacturing plants. A risk assessment for each plant has been completed. Which of the following is the first action of the project manager?


A.

Solicit a request for information


B.

Develop a concept design to solicit support from senior management


C.

Have construction documents prepared and sent to prospective contractors for bids


D.

Develop a phased implementation plan