Question #: 49
Topic #: 5

In the procurement process, the pre-bid conference provides the contractor:


A.

An opportunity for contractors to submit proposals for the project anonymously


B.

An opportunity to ask for any clarifications about information contained in the bid documents


C.

An opportunity to ask other contractors to estimate the total cost of their proposal for comparison


D.

An opportunity for the owner or owner's representative to disclose the expected cost of the project