Better-Business-Cases-Practitioner Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

The new campus scheme will take three years to complete. Projected inflation over this period will mean that staffing costs will be 6%

higher when the campus is operational.

Should this increase be managed as a risk to the project?


A.

No, because inflation should be included as a cost in the Financial Appraisal.


B.

No, because any increase in cost should be dealt with as an issue.


C.

Yes, because any cost increase could threaten the affordability of a scheme.


D.

Yes, because any risk that might affect the financial viability of a scheme should be closely managed.