AgilePM-Practitioner Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

Using the information provided in the additional information, answer the following question on building a change analytics strategy.

Do the measures to be monitored by the Sales Director represent appropriate measures for assessing change readiness?


A.

No, because change readiness measures should consist of mostly quantitative measures.


B.

No, because change readiness should be monitored using the change programme plan.


C.

Yes, because the Sales Director has identified measures that require new data sources.


D.

Yes, because these metrics provide opinions collected via mostly qualitative methods.