APMG-International Agile Project Management (AgilePM) Practitioner Exam AgilePM-Practitioner Question # 34 Topic 4 Discussion

APMG-International Agile Project Management (AgilePM) Practitioner Exam AgilePM-Practitioner Question # 34 Topic 4 Discussion

AgilePM-Practitioner Exam Topic 4 Question 34 Discussion:
Question #: 34
Topic #: 4

Which 2 actions should the Workshop Facilitator take to implement the new

Must Have requirement?


A.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.


B.

Consolidate and circulate an agenda for the workshop.


C.

Send a company-wide communication to explain the implications of the

business change to all interested parties.


D.

Assess the impact of the additional development costs on the original

Business Case.


E.

Encourage all parties to contribute, irrespective of their views.